Schedule Update

We’re chugging along towards the finish-line!

Here’s where things stand for the next couple of weeks:

Feb 25 (today) - 52″ LCD arrived! Priming walls and ceiling.

Feb 26 - Electrician comes to rough-out the soffits and platforms. Paint ceilings flat black.

Feb 27 - Electrician wires up outlets. Pull low voltage wiring through conduit. New Focal Twin6 monitors arrive!

Feb 28 - Install plywood on platforms and soffits. Paint walls.

Mar 3 - Install hardwood flooring. Custom-built rack/Producers Desk arrives.

Mar 4 - Install carpet on platforms. Acoustic panels, diffusor pieces,  and isolation door arrive. MOVE GEAR IN FROM THE TEMPORARY STUDIO!!!

Mar 15 - John Storyk comes for site visit.

Mar 16 - Freddie’s birthday!

Of course, more photos of all these days to come!