Ceiling Channel Going Up

They made some great progress today getting the threaded rods cut and put into all the springs and also put all of the C-channel up in the front of the Control Room. They thought leveling it would be difficult, but with their scaffolding in place, it was fairly quick to run back and forth, adjusting the level of the channel. Next, they have to criss-cross that C-channel with hat-channel, then hang drywall.

We ran into an issue today getting the RPG Modex Plates for the ceiling. We need three plates (two Type-2 and one Type-1) and they hang from the finished drywall ceiling. I just found out today that there is a 4-6 week lead-time in getting these plates. WHAT?? Great. So we’re looking to see if we can get them sooner (or if there’s a suitable replacement product). If not, I guess I’ll order them tomorrow and hope they come in closer to 4 weeks, rather than 6.