VOCOMOTION New Studio Construction Diary

Resilient Channel and IsoMax Clips Done

They finished putting up all the Resilient Channel (RC) and IsoMax clips yesterday. In the photos, the RC is the horizontal steel channels you see on the walls. They are mounted to the existing walls using IsoMax clips, which decouple the next layers of drywall from the underlying wall.

Today, the contractors are boxing in the steel beam that runs through the top of the control room with three layers of drywall. You can see the uncovered beam in one of the pics here. The electrician is coming in Wednesday to do the rough electrical work and the inspection (framing/electrical) is scheduled for Thursday at 10am. On Thursday at 7am, 120 sheets of drywall are being delivered as well.